No less than 65% of the motorway will be curves with a radius of 800 to 6.000 meters. The route is extremely sinuous because designers wanted to avoid demolishing of houses or public buildings.
By the end of this month, the constructors of the Ploiesti-Moara Vlasiei stretch should take over their building sites.
For the Moara Vlasiei-Bucharest stretch, expropriations will follow, the planned spending being 83 million Euros for 1.858 lots of land.